C3Fire criteria · location
Fire compartment
A fire compartment is a part of a building separated on every side, including its ceiling and floor, by walls and floor slabs rated for at least 60 minutes, and it keeps out smoke and heat. Doors and glass in the boundary are fire-rated too. How large it may be depends on the building's use: at most 8,000 m² in offices, 1,500 m² in hospitals.
Compartment lineWall-to-wall glass partition
Door in the lineClosed, fire on the other side
- Fire resistance of the boundary
- At least 60 minutes
- Largest area in offices
- 8,000 m²
- Hospital in-patient floor
- Over 300 m²: split in two
- In high-rise buildings
- At most 3 storeys
- Door and glass in the boundary
- Fire-rated
01 Largest area
What is the maximum size of a fire compartment in m²?
The compartment area is the floor area of the section enclosed by fire-rated walls and floor slabs. If a floor is larger than this limit, it is divided by fire-rated lines running from external wall to external wall. Choose your building and enter the floor area; the plan divides itself.
1What is the building used for?
2compartmentsminimum · this floor
In an office building a compartment is at most 8,000 m² (≈ 89 × 89 m).
With fire control systems such as detection and sprinklers, the limit is 16,000 m²: the floor can be a single compartment.
Source: BYKHY 24(6), Annex 4
02 Line on the plan
Where does the compartment line run on the plan?
Example: a 12,000 m² office floor divided into A and B because the limit is 8,000 m². Choose a rule; its location is marked on the plan.
Uninterrupted from façade to façade
The line runs without interruption from one external wall to the opposite external wall and from floor to ceiling; it is fire-rated at the junctions too. On a curtain wall, the junction between façade and floor slab is insulated for the slab's rating.
ExampleIn an office with a glass façade the line runs right up to the façade; no open joint is left where the façade meets the partition.
Source: BYKHY 24(7), 27(3)(a)
Fire door in the corridor
There can be no non-fire-rated opening between compartments. Where the line cuts across a corridor there is a fire-rated door; a fire-rated glass partition can be placed beside it for light and visibility.
ExampleA double-leaf glazed fire door in the corridor in the middle of the office, with fixed fire-rated glass on both sides.
Source: BYKHY 24(7)
Escape to the neighbouring compartment
People escaping the fire move to the neighbouring compartment on the same floor. Every horizontal evacuation area gives access to at least one protected escape route; each compartment is planned with its own stair.
ExampleWhen fire breaks out in A, staff either go to A's stair or pass through the door into B and go down B's stair.
Source: BYKHY 4(1)(s), 32(7)
Fire damper in the duct
Ventilation ducts should not penetrate the compartment wall. If one air handling unit serves more than one compartment, fire dampers are fitted in the supply and extract ducts at the crossing.
ExampleWhere the duct in the corridor ceiling crosses the line it is cut by a damper; it closes in a fire, so smoke is not carried into B.
Source: BYKHY 87(6), 87(8)
Shafts aligned with compartments
Services risers and ducts that play a part in fire spread are aligned with the compartment and insulated so as not to reduce the compartment's fire resistance.
ExampleEach compartment's services shaft stays within it; no shaft is placed on the line.
Source: BYKHY 87(11)
03 Boundary line
What requirements apply at the compartment boundary?
First the line itself, then its junctions with ceiling, wall and floor; tapping a tab locks the view.
1 / 2 · Boundary lineThe fire in the neighbouring compartment is fully developed; this side is calm. The line keeps the fire in its own section.
- Glass wallThe separating element is rated for at least 60 minutes; the glazed partition carries this class with its certification.
- DoorThere can be no non-fire-rated opening between compartments; the door in the line is fire-rated too.
- Ceiling slabA compartment is separated on every side, including its ceiling and floor slabs; the line rises to the slab.
Source: BYKHY 4(1)(tt), 24(1), 24(7)
2 / 2 · JunctionsThe weak points of the line are the junctions: no gap is left at the ceiling, side wall or floor.
- Ceiling junctionThe fire resistance of the elements enclosing the compartment is continuous at the junctions too.
- Side wallThe wall the line connects to is also a compartment wall; if it separates different uses it is at least REI 60.
- Floor slabAll floor slabs have the quality of a fire wall; the rating of a compartment floor is read from Annex 3/C.
Source: BYKHY 24(7), 26(1), Annex 3/B
04 Where in the building
Where does the compartment boundary run in the building?
Section A-A: a 10-storey office building with a basement. The stair and lift shaft form a separate protected core, and the compartments lie outside it. Choose a rule; that compartment appears in orange on the section.
A compartment is a box
A compartment is enclosed not only by walls but also by the floor slabs below and above it. All six faces are rated for at least 60 minutes; all floor slabs have the quality of a fire wall.
ExampleIf an office floor is a compartment, its floor and ceiling are also part of the boundary; fire does not pass to the floor below or above.
Source: BYKHY 4(1)(tt), 26(1)
In high-rise buildings, at most 3 storeys per compartment
If the building is taller than 21.50 m (30.50 m for residential), the floors above this height are grouped into compartments of at most three storeys each. The slab between groups is a compartment boundary.
ExampleIn a 35 m office building, the +24.50, +28.00 and +31.50 floors above 21.50 m can form one compartment.
Source: BYKHY 24(4)
Car parks and plant rooms are separate compartments
Car parks, boiler rooms, main electrical rooms, transformer and generator rooms, whatever their area, are separated from the rest of the building by walls and slabs with the quality of compartment walls.
ExampleEven if the basement car park is small, the slab above it and its wall opening onto the lift lobby are a compartment boundary; the door here is fire-rated too.
Source: BYKHY 24(2), 24(7)
Between different uses
If different activities, such as a shop and an office, take place in the same building, the wall between them is a compartment wall: at least REI 60 or the duration in Annex 3/C for the building class and height, whichever is greater.
ExampleIn a building with a shop on the ground floor and offices above, the glass wall and door separating the shop from the office lobby are fire-rated.
Source: BYKHY Annex 3/B, Annex 3/C
A floor exceeding the area limit is divided
If a floor exceeds the largest compartment area for the building's use, a fire-rated line is drawn within the floor: wall, glass partition and door. The limit comes from the calculation in 01.
ExampleA 12,000 m² office floor (limit 8,000 m²) is divided into at least two compartments; the line between them is rated for at least 60 minutes.
Source: BYKHY 24(6), 24(7), Annex 4
05 Four locations
Where is a compartment line most often built?
Four locations, and in all four the door and glass in the line are fire-rated. Tap a location and the properties the article requires light up.
Fire side
Safe side
- Line dividing a large open-plan office In an office building, if a floor exceeds 8,000 m² (16,000 m² with suitable fire control systems), the open-plan office is divided by a line rated for at least 60 minutes; the door and glass in the line are fire-rated too. BYKHY 24(6), 24(7), Annex 460 Office building page
- Line splitting a hospital ward floor in two In hospitals and care homes, every in-patient floor larger than 300 m² is divided into two or more compartments, each at least half the floor's size, or a protected horizontal evacuation area is provided. Patients move away from the fire into the neighbouring compartment on the same floor. BYKHY 49(1)(b), 4(1)(s)60 Hospital page
- Car park door to the lift lobby The walls and floor slabs of car parks, boiler rooms, main electrical rooms, transformer and generator rooms have the quality of compartment walls. The door from such a space into the building is fire-rated too. BYKHY 24(2), 24(7)60
- Between a shop and an office lobby A compartment wall separating different uses within a building is rated for at least REI 60 or the duration in Annex 3/C for the building class and height, whichever is greater. BYKHY Annex 3/B, Annex 3/C, 24(7)60+ Shopping centre page
06 Your project
Where should the compartment line run in your project?
These four answers change the line's location and rating.
- 01
What is the building's use?
8,000 m² in offices, 4,000 in hotels, 1,500 in hospitals; in mixed use the uses are also separated from each other.
- 02
Is there a fire control system?
With detection, sprinklers and smoke extraction, the area doubles or becomes unlimited.
- 03
How tall is the building in metres?
In a non-residential building over 21.50 m, the upper floors form compartments of at most three storeys each; the rating rises with height.
- 04
Is there a door or glass in the line?
Every opening between compartments is fire-rated; the door and glass are chosen to match the line's rating.
Let us specify the glass and door in your compartment line together. Send the plan and building details; our technical team will review them.
Send the project07 Boundary in glass
Can we build the compartment boundary in glass?
We make it with Aliplast profiles and Polflam glass to the line's rating and dimensions.
Framed partition
EI30 – EI120
Floor-to-ceiling, non-opening glass wall; up to 60 minutes with FR65, 120 minutes with FR90. Fixed glass partition
Frameless partition
Uninterrupted glass
Without vertical profiles, 30–120 minutes with Polflam BR glass. Frameless glass partition
Door in the line
Single or double leaf
FR65 and FR90 glazed doors are also made in class EI60. Double leaf
The class is given by a certificate in which glass and profile were tested together; the partition height and glass size stay within the scope of the certificate. Fire-rated glass partition
Abay Yapı Sistemleri
Trusted for 30 years.
We make the glass partitions and doors for compartment lines with Aliplast profiles and Polflam glass, to each project's dimensions in our Istanbul workshop.
- 154
- corporate references
- Aliplast
- authorised manufacturer and distributor in Turkey
- Polflam
- partner for fire-resistant glass
- Istanbul
- head office and production, Istanbul



- 01Project and useBuilding type, required rating, door location
- 02Size and openingOverall size, clear width, opening direction
- 03System and hardwareProfile, glass, lock, closer
- 04Quote and productionScope agreed, delivered with the document set
Projects
Glass partition and door lines from our reference projects.
Top row: our glass partition installations; bottom row: passage doors in the line. Tap a photo; browse with the arrows.
08 Document set
Which documents are required for the glass and door in a compartment line?
The line's fire resistance is shown with separate documents for the partition and the door.
Four checks at handover
- Fire resistance. The minutes in the report must not be less than the duration the line requires.
- Partition and door separately. The glass partition and the door in the line must each have their own classification report.
- Size. The partition height and glass size must stay within the scope of the report.
- Declaration and CE. A declaration of performance issued for the product and the CE marking are required.
- ClassificationPartition classification reportWith the project's height and glass sizeRequest
- ClassificationDoor classification reportSingle or double leafRequest
- DeclarationDeclaration of performanceCE markedRequest it
- DrawingCeiling, wall and floor junction detailsDWGRequest
Source: Turkish Construction Products Regulation 6(1), 10(2)
Request the document set for the compartment line. Documents are sent together with the line's rating and dimensions.
Request the document set09 FAQ
About fire compartments
The compartment line and its rating are set by the project architect, the fire consultant and fire brigade approval. These articles are a starting point; let us draw together where the line will run in your project.
What is a fire compartment?
A part of a building separated on every side, including its ceiling and floor slabs, by building elements rated for at least 60 minutes, which keeps out smoke and heat. It keeps a fire in the section where it started; people escape by moving to the neighbouring compartment.
Source: BYKHY 4(1)(tt), 4(1)(s)
What is the maximum size of a fire compartment in m²?
It depends on the building's use: 8,000 m² in offices, 4,000 in hotels, 1,500 in hospitals, 2,000 in commercial buildings, 6,000 in educational facilities. With suitable fire control systems the area can be doubled in offices, hotels and hospitals, and is unlimited in commercial and educational buildings.
Source: BYKHY 24(6), Annex 4
How many minutes must a compartment wall resist fire?
At least 60 minutes. A wall separating different uses is rated for REI 60 or the duration in Annex 3/C, whichever is greater. For example, in an office building without sprinklers, 60 minutes if the building height is below 21.50 m, 90 minutes if below 30.50 m.
Source: BYKHY 4(1)(tt), Annex 3/B, Annex 3/C
Can there be a door or glass in the compartment boundary?
There can be no non-fire-rated opening between compartments, and the fire resistance of the enclosing elements is continuous at the junctions too. So the door and glass partition in the line are fire-rated and carry the line's rating with their certification.
Source: BYKHY 24(7)
What is the difference between a fire compartment and a fire wall?
A compartment is a section within a building, with a boundary rated for at least 60 minutes. A fire wall separates adjoining (terraced) buildings from each other and is rated for at least 90 minutes; doors and fixed glazing in it are rated for at least half the wall's rating, and its door is self-closing and smoke-tight.
Source: BYKHY 4(1)(tt), 25(1), 25(2)
How are compartments arranged in a high-rise building?
In non-residential buildings taller than 21.50 m and residential buildings taller than 30.50 m, the floors above these heights are arranged with at most three storeys per fire compartment.
Source: BYKHY 24(4)
What should a fire compartment be like in a hospital?
Every in-patient floor larger than 300 m² in hospitals and care homes is divided into two or more fire compartments, each at least half the floor's size, or protected horizontal evacuation areas are provided. In a healthcare building a compartment is at most 1,500 m².
Source: BYKHY 49(1)(b), Annex 4
→ Quote
Describe your compartment line.
Building use, length and height of the line, doors in the line: our technical team will set the class and document set and get back to you.
- Phone
- +90 216 428 38 20
- abay@abayyapi.com
- Production
- Istanbul